10

Specialist bedrooms

1,482m²

Space over two storeys

84

Roof-mounted solar panels

The Kingfisher, Blackberry Hill, Bristol

Specialist facility bringing an end to long-distance placements across the South West, delivered on a live NHS hospital site through ProCure23

Ending long-distance placements across the South West

Willmott Dixon has completed The Kingfisher, a £20 million, 10-bed specialist inpatient facility on the Blackberry Hill site in Bristol for Avon and Wiltshire Mental Health Partnership NHS Trust (AWP). Handed over in August 2026, the building was purpose-designed for people with a learning disability and autistic people who need specialist mental health care that cannot be provided in a mainstream hospital or at home.

Patients in this group have historically travelled long distances for that care. The Kingfisher was built to bring those placements to an end across the northern half of the South West, keeping people closer to their families, friends and carers. Bath and North East Somerset, Swindon and Wiltshire Integrated Care Board led the commissioning on behalf of neighbouring ICBs, and the facility forms one half of a coordinated regional offer alongside a companion unit in Devon, the first time systems across the South West have worked together to deliver these services.

Designed with lived experience at its heart

Over an 18-month period, groups representing people with a learning disability and autistic people met the design team to shape the building from the inside out: ward layout, furniture design, garden landscaping and sensory considerations such as acoustics and lighting. That contribution is visible throughout the completed facility, and it set the standard for how the project team worked with the Trust from preconstruction through to handover.

What we delivered

The scheme involved demolishing the existing building and constructing a purpose-built specialist unit in its place:

  • A 1,482m² two-storey inpatient unit providing 10 specialist bedrooms, fully integrated into the wider Blackberry Hill site.
  • Therapeutic internal environments shaped by people with lived experience, acoustics, lighting, furniture and sensory design.
  • Landscaped external and garden space designed with service users, families and carers.
  • A fully electric, gas-free building served by air source heat pumps, with no reliance on fossil fuels for heating or hot water.
  • 84 roof-mounted solar panels totalling 37.38 kWp, generating an estimated 33,390 kWh of renewable electricity a year.
  • A sustainable drainage solution using an ACO Roofbloxx attenuation crate system, engineered for a tightly constrained urban site.

PROJECT DETAILS

PROJECT HIGHLIGHTS

  • 10-bed specialist inpatient facility for people with a learning disability and autistic people
  • 1,482m² across two storeys, delivered on a live, operational hospital site
  • 71% MMC score against the ProCure23 MMC Toolkit, exceeding the NHS 70% minimum
  • Gas-free, all-electric building with air source heat pumps and 37.38 kWp of rooftop solar PV

Built within a live, operational hospital setting

The Kingfisher was constructed on a working hospital site with limited space and live neighbouring services. We answered that constraint with modern methods of construction, achieving an MMC score of 71% against the ProCure23 MMC Toolkit and exceeding the NHS minimum of 70%. Panelised wall and floor systems, prefabricated stair and lift shafts, pre-hung doorsets, prefabricated sanitary systems and pre-assembled mechanical and electrical modules moved work off site, shortening installation periods, improving quality and consistency, and reducing waste and embodied carbon.

A low-carbon building, verified in performance

The facility achieved a Design Stage BREEAM Excellent rating of 76.5% under BREEAM UK New Construction v6 (Healthcare), comfortably above the 70% threshold, and is on track for BREEAM Excellent at post-construction stage. A fabric-first approach delivered a measured air permeability of 2.79 m³/h·m² at 50 Pa against a target of 3.00, and the exclusive use of HVO fuel on site prevented 2,217.49 kg CO₂e from entering the atmosphere during construction.

£5.3 million of social value for Bristol and South Gloucestershire

The project generated a total social value outcome of £5.31 million. Willmott Dixon procured £6 million of goods and services from locally based supply chain partners and achieved £8.8 million of SME supply chain spend. The team delivered 1,111 apprentice weeks with 30 apprentices working on the scheme, 45 weeks of work experience, 135 hours invested in local schools and 1,400 pupil interactions across 44 educational engagement activities. The site scored 44 out of 45 under the Considerate Constructors Scheme, and a legacy project with Grow Wilder, the urban hub of Avon Wildlife Trust, left lasting improvements worth more than £13,000 to a site used by thousands of visitors each year.

What people are saying

“Being part of this project has been a real privilege. Working so closely with the AWP team created a genuinely collaborative environment where everyone was focused on delivering the very best outcome. Seeing The Kingfisher come to life and knowing the difference it will make for people and their families across the region is something the whole team can be proud of.”

Paul Rice, Senior Operations Manager, Willmott Dixon

“It has been very rewarding and confidence building to have our thoughts and ideas listened to… We are committed to keeping the autistic voice at the forefront of any ward/clinical design so that the environment is adapted to our needs.”

Ben Stunell, peer mentor