Context and significance
Greater Manchester has set one of the UK’s most ambitious public transport targets: a fully zero-emission bus fleet by 2030. Central to it is the Bee Network, the city region’s integrated transport network, launched as Transport for Greater Manchester (TfGM) brought buses back under public control. Three years ago, just 35 electric buses were in service. Today there are more than 500 – and every one of them needs reliable power to charge.
Willmott Dixon has completed £15.6m of electrification works at two existing, operational bus depots – Hyde Road in Manchester and Oldham town centre – procured through the SCAPE Construction Framework. The upgraded Oldham depot, operated by Stagecoach, received the Bee Network’s 500th zero-emission bus, a milestone in the region’s transition to cleaner public transport.
What we delivered
- 138 EV chargers across the two depots
- A new private high-voltage substation, together with low-voltage distribution
- Associated civils and builders’ work to connect the chargers to the network
- Works delivered within two existing, operational bus depots
- A 29-week pre-construction phase followed by a 35-week construction programme, January to September 2026